FFYs 2018-2022 Transportation Improvement Program (TIP) Draft Amendment Six Summary

  Overall Changes in Funding in TIP
Project Proposed Change Explanation Section/Funding Source From To Difference
604804; Reading - Resurfacing and Related Work on Route 28 (Main Street) DECREASE COST Cost decrease due to final design. Section 2A/Non-Interstate Pavement $7,424,556 $6,063,543 ($1,361,013)
608008; Saugus - Resurfacing and Related Work on Route 1 INCREASE COST Cost increase due to final design. Section 2A/Non-Interstate Pavement $9,812,880 $11,076,010 $1,263,130
606381; Cambridge - Arlington - Belmont - Lexington - Highway Lighting Repair and Maintenance on Route 2 INCREASE COST Cost increase resulting from changes in scope:

 - Inclusion of Roadway Lighting on the Alewife Station Access Road.

 - Relocation of some of the Roadway Lighting on Route 2 from the outside edges of Route 2 to the median.

 - Installation of lighting at the Dow Street underpass.

 - Inclusion of ITS cameras and components.
Section 1B/Other Federal Aid (Earmark)

Section 2A/Safety Improvements
$14,178,273 $15,714,202 $1,535,929
606632; Hopkinton-Westborough- Bridge Replacement, Fruit St. over CSX and Sudbury River REMOVE PROJECT Project advanced to 75% design; some design and environmental concerns resulted in the need for additional design and review time.  Section 2A/Bridge Program/Off-System $11,465,706 $0 ($11,465,706)